Skip to content
SuperCharge.SG

Guide · Commercial EV charging

Choosing a DC fast charger in Singapore: AC vs DC for businesses (2026)

How to decide between AC chargers and a DC fast charger in Singapore: start with how long vehicles stay, then check your power supply, the LTA rules and how you will run and bill the chargers.

By SuperCharge.SG · Published · Sources read 14 Nov 2026 · 9 min read

A DC fast charger is the most visible piece of EV infrastructure a Singapore business can buy, and often the most expensive to connect. It is the right answer for some sites and an expensive mistake for others. The deciding question is not how fast the charger is, but how long your vehicles and visitors actually stay.

This guide walks through that choice in the order a facility manager meets it: dwell time, charger power, the electricity supply, the LTA rules under the Electric Vehicles Charging Act, and how the chargers will be managed and paid for. Regulatory facts link to the official page they came from.

AC charger or DC fast charger? Start with dwell time

AC chargers pass alternating current to the car, and the car's own onboard charger converts it for the battery, so the car sets the ceiling on AC charging speed. A DC charger does the conversion inside the unit and feeds the battery directly, which is why it can deliver far more power, and why it needs a much bigger electrical supply.

Match the charger to the time a vehicle is parked:

Matching charger type to how long vehicles stay
Typical stayExamplesUsually fits
Several hours or overnightOffice staff, pool cars, hotel guests, depot vans parked overnightAC, up to 22 kW
One to two hoursRetail and dining visitors, showroom test drivesAC, or a lower-power DC charger
Under an hour, or vehicles back on the road between shiftsDelivery and ride-hail fleets, fast turnaround sitesDC fast charger

Many sites end up with both: a row of AC chargers for long stays, plus one or two DC units for the vehicles that cannot wait.

30, 60 or 120 kW DC charger: what the numbers mean

A DC charger's rating is its maximum output. Energy delivered is power multiplied by time, so a simple ceiling is easy to work out: a 30 kW charger can supply at most 15 kWh in 30 minutes, a 60 kW charger at most 30 kWh and a 120 kW charger at most 60 kWh. Real sessions deliver less, because the car only accepts full power within a range of battery charge and temperature, and slows down as the battery fills.

  • 30 kW DC: compact, easier on the supply, suits sites where vehicles stay an hour or so.
  • 60 kW DC: a middle option for fleets and busy commercial car parks.
  • 120 kW and above: for high-turnover fleets and public hubs, sometimes with two connectors that share the output.

Check what your vehicles can accept before you size the charger. A car or van whose maximum DC charging power is below the charger's rating will not charge any faster on the bigger unit. The vehicle's specification sheet gives its maximum AC and DC charging power.

Connectors for chargers the public can use

Publicly accessible locations may only use fixed chargers with Type 2 AC and/or CCS2 DC connectors; CHAdeMO connectors may only be provided in addition to them.[3]

Power supply for a DC fast charger in Singapore: LEW and SP Group

Electrical capacity is usually the deciding factor for a DC charger in Singapore, and the step with the longest lead time. Applications to connect to SP Group's network, or to increase a site's approved load or contracted capacity, are submitted by a Licensed Electrical Worker (LEW) acting as the customer's agent.[7]

SP Group's connection handbook sets out the thresholds that matter for car park projects:[7]

  • Low-tension supply is 230 V single-phase, up to 23 kVA, or 400 V three-phase.
  • A direct connection from SP's low-tension network is available for loads up to 280 kVA, if there is enough network capacity nearby.
  • Above 280 kVA, the customer must provide a substation for SP's equipment.
  • SP's planning assumes a power factor of 0.85.

As an illustration only: four 60 kW DC chargers running at full output draw 240 kW, which at a 0.85 power factor is about 282 kVA, already past the 280 kVA direct-connection limit before the rest of the building's load is counted. Load management, which shares a set power limit between smart chargers, can keep the total lower.

Site planning for commercial EV chargers

Beyond the supply, a few physical factors drive the scope and cost of a commercial EV charger installation:

  • Cable route: the distance from the switchboard to the charging bays, and whether cables run on trays, through ducts or under the car park surface.
  • Transformer and switchboard space: whether the existing equipment has spare ways and capacity, or needs upgrading.
  • Bay layout: DC units are larger than wall boxes and need protection such as kerbs or bollards, plus room for cables to reach charge ports on either side of a car.
  • Network connection: smart chargers need a reliable Ethernet, Wi-Fi or 4G link to their management platform.
  • Ventilation and heat: DC chargers produce heat, so keep their intakes and exhausts clear.

New buildings, and buildings undergoing significant building and electrical works, must install a minimum number of EV chargers and provide sufficient electrical capacity for charging.[1] If your site is due for major works, that is the cheapest time to build in DC-ready capacity.

SS 722, LTA registration and inspections for DC chargers

Singapore's national EV charging standard is SS 722, which superseded TR 25 on 1 April 2026.[1] Chargers already type-approved under the earlier TR 25 standards do not need to be re-certified to SS 722, and new charger models have a transition period before SS 722 compliance becomes mandatory.[2] When you compare quotes, ask for chargers that are LTA type-approved and compliant with TR 25 / SS 722.

Every charger must be type-approved by LTA before it can be installed, certified and registered. A Licensed Electrical Worker installs it, a certified charger equipment specialist certifies it, and the owner must register it with LTA before it is used.[4] A commercial car park is not a restricted-access (landed) location, so these fees apply:[5]

LTA registration fees for non-restricted (shared) chargers, per LTA's registration page (updated 17 Sep 2026)
Charger powerRegistration feeTypical charger
Below 23 kWS$150AC up to 22 kW
23 to 150 kWS$37530, 60 or 120 kW DC
Above 150 kWS$600High-power DC hub

Shared chargers must then be inspected every 6 months by an equipment specialist, or every 12 months by an LEW, and the certificates kept for at least two years.[4] Our EV charger installation guide explains the registration steps in more detail.

Offering charging to staff, visitors or the public: the EVCO licence

Under the Electric Vehicles Charging Act, anyone who operates charging stations serving members of the public, or provides EV charging services, needs an EV Charging Operator (EVCO) licence from LTA. LTA's examples include operators of chargers serving office employees, other commercial building users and visitors.[6] Fleet owners who operate chargers only to charge vehicles in their own fleet do not need a licence, but an operator who runs chargers on behalf of a fleet owner does.[6]

  • Each licence is valid for three years.[6]
  • Licensees must hold third-party liability insurance and keep a minimum service uptime of 90% across their charging points.[6]
  • Licence conditions also include sharing charging data with LTA.[1]

Charger owners can apply for the licence themselves or engage a licensed EVCO to operate the chargers for them.[6] Decide this early, because it affects the contract, the software you need and who answers for uptime.

Payment, access and OCPP management for business chargers

A smart charger that speaks OCPP, the open charge point protocol, can be monitored, controlled and billed from a charge point management system (CPMS) rather than being tied to one brand's app. For a business that means choosing who may charge, setting tariffs for staff, visitors or the public, seeing faults remotely and sharing a limited supply between chargers.

SuperCharge.SG runs chargers on its own OCPP platform, which works with most OCPP 1.6 chargers and provides real-time monitoring, remote diagnostics, user access and billing, and the charging data LTA requires from licensed operators. See the OCPP charging platform for details, or our commercial and DC fast charging service for how we survey a site and size the supply.

Heavy vehicle operators should also look at LTA's Electric Heavy Vehicle Charger Grant, which co-funds chargers rated at least 50 kW for new electric heavy vehicles, at heavy vehicle lots.[8]

FAQ

Frequently asked questions

Should my business install AC or DC chargers?

Base it on how long vehicles stay. Where cars park for several hours, AC chargers up to 22 kW are usually enough and cost less to connect. DC fast chargers suit vehicles that must turn around in under an hour, such as delivery and ride-hail fleets. Many sites use both.

Is a 60kW or 120kW DC charger better?

Only if your vehicles can use the extra power. A vehicle charges no faster than its own maximum DC rating, and the higher rating needs more electrical capacity. Compare your fleet's DC limits, daily energy needs and the spare capacity at your switchboard before choosing.

Will a DC charger need an SP Group supply upgrade?

Often, yes. SP Group offers a direct low-tension connection for loads up to 280 kVA where the network allows; above that the customer must provide a substation. An LEW submits the application on your behalf (SP Group handbook, Nov 2026).

How much is the LTA registration fee for a commercial DC charger?

For a non-restricted (shared) charger rated 23 to 150 kW, which covers most 30, 60 and 120 kW DC chargers, the LTA fee is S$375. Above 150 kW it is S$600, and below 23 kW it is S$150 (LTA registration page, updated 17 Sep 2026).

Do I need an EVCO licence to install a DC fast charger in Singapore?

If the charger serves the public, staff, building users or visitors, the operator needs an EVCO licence from LTA. Fleet owners charging only their own fleet vehicles do not, though a third party operating chargers for them does. You can also engage a licensed EVCO to operate the chargers for you. A licence is valid for three years.

How often must a commercial DC charger be inspected?

Shared chargers must be inspected every 6 months by a charger equipment specialist, or every 12 months by a Licensed Electrical Worker, with certificates kept for at least two years.

Sources

Every source below was read on 14 Nov 2026. Grants, fees and tariffs change, so check the source before you rely on a figure.

  1. [1]Electric vehiclesMinistry of Transport, last updated 25 Aug 2026. Read 14 Nov 2026.
  2. [2]Singapore elevates national standard for EV charging systemsLTA and Enterprise Singapore, 31 Mar 2026, updated 1 Apr 2026. Read 14 Nov 2026.
  3. [3]Guidelines for the supply of electric vehicle chargersLand Transport Authority, as of 15 Oct 2025. Read 14 Nov 2026.
  4. [4]Guidelines for the registration of electric vehicle chargersLand Transport Authority, as of 3 Nov 2025. Read 14 Nov 2026.
  5. [5]Registration of EV chargersLand Transport Authority, last updated 17 Sep 2026. Read 14 Nov 2026.
  6. [6]Guidelines for the licensing of EV charging operatorsLand Transport Authority, as of 21 Nov 2025. Read 14 Nov 2026.
  7. [7]How to Apply for Electricity Connection (handbook)SP Group, Nov 2026 edition. Read 14 Nov 2026.
  8. [8]Electric Heavy Vehicle Charger Grant: guidelines and FAQsLand Transport Authority, accurate as of 1 Dec 2025. Read 14 Nov 2026.

Get advice for your own property

Every site is different. Tell us about yours and we will recommend the right setup, with a written quote.